Friday, July 18, 2008

Friday




After the rain delay on Thursday, the P.O.P. ers came back strong. We got the insulation and vapor barrier done (inspection passed), the retaining wall built (garage slab on Monday), and the siding almost finished. All in all a really good week. Thank you for all of your hard work.








































More Rain


Once more rain disrupts our Thursday, although no tornado sirens this week.

Prince of Peace LC

Other than the counseling session about proper scaffolding assembly, it was a fun week with P.O.P. Some of our volunteers had a chance to catch some rays as well as installing siding and insulation.


























































































Monday, July 14, 2008

Josh on the phone with his agent







How exciting is this


This one deserves its own post. We really try to keep our volunteers engaged and excited. Not always successfully.

The end of the week with Gethsamane LC

We finished out the week with stairs, more framing in the trusses, and siding. We only had to take off a little and do it over (my fault)












































And then the sirens went off











This is what it looked like when the tornado sirens went off, sending us all into the basement
Three days with Gethsamane LC. We "finished" the framing, and started siding



































After a week break, and a basement floor we are back at it. We framed the basement rooms and started soffit and fascia.